Tuesday, December 1, 2009

Tues

Tuesday, Dec. 1: The front door got holes cut for the doorknob and lock. (We just have to apply the gel stain, put on the doorknob, deadbolt, and re-hang.) Rock was delivered so there's another layer on the existing driveway and also we created a circle drive (just have to smooth it out.) Chris framed the west wall of the basement (that was poured concrete) and got started doing headers and such for the rooms down there. Tuesday evening he and a friend, Adam Quinn, put together and hung the garage door.